Skip to Navigation Skip to Main Content Skip to Footer
 

Cleco offers restoration and damage updates

Lineman Restoring Power
Sep 4, 2021

PINEVILLE, La. – Sept. 4, 2021 (8:30 a.m.) – Cleco continues restoration efforts with power restored to 73 percent of customers in St. Tammany Parish and 47 percent of customers in Washington Parish. 

Restoration Estimates
Below are estimated times for restoration (ETR).  Additional ETRs will be shared, as they become available.  Please note that unexpected damage or inclement weather could impact restoration efforts and timelines. 

St. Tammany Parish

  • Covington ETRs as of Saturday, Sept. 4
    • Robinhood 7-8 days
    • Riverwood 8-10 days
    • Covington Country Club 4-5 days
    • Lee Rd.  8-10 days
    • White Chapel Rd.  4-5 days
    • Sunshine Ave. 8-10 days
    • Oak River   8-10 days
    • River Parc 8-10 days
    • Tammany Hills 8-10 days
  • Madisonville ETRs as of Saturday, Sept. 4
    • Del Oaks 8-10 days
  • Mandeville ETRs as of Saturday, Sept. 4
    • Marigny Trace 2-4 days
    • Colbert St.  2-4 days
    • Old Golden Shores 4 days
    • Brookside Dr.  8-10 days
  • Lacombe as of Saturday, Sept. 4
    • ETR is 2-4 days
      • Laura Oaks
      • Blackwell Dr. area
      • Hwy 190 West of Ponchartrain
      • Autumn Haven
      • Beau Village
      • Hwy 190 Thompson St.
      • Jackson St.  

Power Restoration as of 8:30 a.m.  

Parish

Customers with Power

Customers Served

Percent of Customers with Power

St. Tammany

70,752

96,974

73%

Washington

378

799

47%

 

Damage Report as of 8:30 a.m.

Broken Poles

Damaged Transformers

Damaged Crossarms

Conductor Down (spans)

Trees On Line

Total

533

375

1,754

4,243

2,834