PINEVILLE, La. – Sept. 4, 2020 – As of noon today, Cleco had restored power to 52 percent of the customers in Grant Parish impacted by Hurricane Laura.
Restoration Assessment
Below are restoration estimates. Please note that unexpected damage could impact restoration efforts and timelines. Cleco will report updates on areas as they become available on Facebook @ClecoPower and Cleco’s website at cleco.com.
Pollock
- Friday, Sept. 4
- Barron Road off Hwy 165 N
- Humphries off Hwy 165 N
- Crawford Loop
- Martin Acres
- Sherwood Forest
- Springhill Road and Springhill Loop
- Saturday, Sept. 5
- One town water well
- Lumberton subdivision
- Crews are working on Dyson Circle Road and expect a 2-3 day restoration effort
- Monday, Sept. 7
- The main line on Hwy 8 toward Fishville – Bodies Landing
- Thursday, Sept. 10
- Camp Hardtner area from Hunt Plywood Plant
Colfax
- Friday, Sept. 4
- Control House Road and Youngblood Road
- Dixon Hill Road
- Slayter Nichols Road
- Saturday, Sept. 5
- Main line on Hwy 8 South
- Sunday, Sept. 6
- Nantachie area
- Monday, Sept. 7
- Katherine Cove
- US 71 and Smith Road
- Friday, Sept. 11
- Iatt Dam Road – Hyde Landing – Abe Hall Road
Dry Prong
- Friday, Sept. 4
- Larry Braxley Road – Bethel Church Road
- Sunday, Sept. 6
- Hwy 123 W
- Friday, Sept. 11
- Landfill Rd / Liberty Chappel Road
- Crews began working on Nelms Loop today, Friday, Sept. 4. No estimated restoration time at this time.
Bentley
- Work on Hwy 8 from Bentley going west to Parsonage Road, Grey Circle Road, Tommy Smith Road and Mundy Loop is ongoing
- Expect to restore power today, Friday, Sept. 4 to some customers along Hwy 8